You have asked three builders to price your renovation, and the quotes are tens of thousands of dollars apart. Which one is right? When you compare builder quotes, the lowest price is rarely the lowest final cost. The real answer comes from checking whether each quote covers the same scope, the same allowances and the same exclusions.
This guide explains why quotes differ so much, what to look for line by line, and how to compare builder quotes in Dunedin with confidence before you sign anything.
Why do builder quotes differ so much?
Most homeowners assume a big price gap means one builder is overcharging. In practice, the gap usually comes from different assumptions. Each builder reads your plans, fills in the gaps and prices what they think you want.
For example, one quote may include new insulation, while another assumes the existing insulation stays. One builder may allow for a mid-range kitchen, whereas another allows for a budget range. Neither is wrong. However, the quotes are no longer describing the same job.
Older Dunedin homes add another layer. Villas and bungalows often hide moisture, tired framing or older wiring behind the walls. Some builders price a contingency for this. Others leave it out and deal with it later as a variation.
Estimate or quote: know what you are holding
Before you compare builder quotes, check what kind of price each document actually is. The difference matters.
- An estimate is a best guess, not a fixed price. According to MBIE’s guidance on tenders and quotes, the final cost is commonly expected to land within about 10 to 15 per cent of an estimate.
- A quote is a detailed price for building to your plans and specifications. It is far more useful for comparison, although costs can still change through agreed variations.
As a result, comparing an estimate from one builder with a detailed quote from another can be misleading. Ask every builder for the same type of price.
How to compare builder quotes line by line
The easiest way to compare builder quotes is to put them side by side and check the same items in each one. Look for these details:
- Scope of work: Does each quote describe the same rooms, walls, finishes and services?
- GST: Is the price GST-inclusive or exclusive? A small line of text can change the total by 15 per cent.
- Labour and materials: Is there a breakdown, or just one lump sum?
- Hourly rate for extra work: What will you pay if something unexpected comes up?
- Consent and design costs: Are council fees, engineering and plans included or excluded?
- Site costs: Have scaffolding, skip bins, protection and clean-up been allowed for?
- Timeframe and payment schedule: When does work start, and when are payments due?
If one quote is much higher or lower than the others, ask the builder to explain why. A good builder will be happy to walk you through their numbers.
Provisional sums and PC sums: the hidden budget risk
Allowances are where many budgets quietly fall apart. Most renovation quotes include at least a few of them.
A provisional sum is money set aside for work that is not yet fully defined. A prime cost (PC) sum is an allowance for an item you will choose later, such as tapware or a benchtop. If your final choice costs more than the allowance, you pay the difference.
Here is the catch. A builder can make a quote look cheaper simply by setting low allowances. So, when you compare builder quotes, check each allowance against what you actually plan to buy. For instance, a $1,500 allowance will not cover a $4,000 vanity.
Our article on how we prevented a renovation variation from becoming a budget blowout shows how this plays out on a real Dunedin project.
Red flags to watch for in a renovation quote
Not every low price is a warning sign. Still, some patterns deserve a closer look:
- A single lump-sum price with no breakdown.
- Vague wording such as “allow for bathroom” with no detail.
- No mention of exclusions at all.
- Pressure to sign quickly or pay a large deposit up front.
- No written contract offered for a large job.
- Reluctance to share their licence details or references.
Ask about licensing early. Restricted building work must be carried out or supervised by a Licensed Building Practitioner. You can check a builder on the MBIE public LBP register and learn about the different LBP licence classes.
What New Zealand law requires before you sign
Knowing your rights makes it easier to compare builder quotes fairly. Under MBIE’s consumer protection measures:
- A written contract is required for residential building work costing $30,000 or more, including GST.
- For work likely to cost $30,000 or more, the builder must give you a disclosure statement and checklist before you sign. You can also ask for them on smaller jobs.
- Builders must fix defects you notify in writing within 12 months of completion.
In addition, implied warranties can protect you for up to 10 years after the work is completed. Rules can change, so check the current details on building.govt.nz before you sign.
A simple checklist to compare builder quotes
Use this checklist when the quotes arrive. Take it to every builder meeting.
- Are all quotes based on the same plans and the same written scope?
- Is each price clearly GST-inclusive or exclusive?
- Have you listed every provisional sum and PC sum side by side?
- Do the allowances match the finishes you actually want?
- What is excluded, and who pays for it?
- Is there a contingency for hidden issues in an older home?
- Is the builder an LBP, and have you checked the register?
- Will you receive a written contract, disclosure statement and checklist?
- How are variations priced and approved?
- Have you spoken to past clients or read homeowner reviews?
Frequently Asked Questions
How many quotes should I get for a renovation?
MBIE recommends getting at least three detailed quotes. More important, however, is making sure every builder prices the same scope.
Should I always choose the cheapest builder quote?
Not necessarily. A lower quote may have lower allowances or more exclusions. Therefore, compare what is included before comparing the total.
What is a PC sum in a building quote?
A prime cost sum is an allowance for an item you choose later, such as fixtures or appliances. If your choice costs more, you pay the difference.
Do I need a written contract for a small renovation?
A written contract is legally required for residential work costing $30,000 or more, including GST. For smaller jobs, a written contract is still strongly recommended.
Can the final price be higher than the quote?
Yes, if the scope changes. Variations, unexpected site conditions and allowances that run over can all add cost. Check how your contract says variations are priced and approved.
How do I check if a builder is licensed?
Search their name on the public LBP register. It shows their licence class and any disciplinary history.
Ready to compare builder quotes with confidence?
At Precision Builders Otago, we would rather you understand your quote than simply sign it. That is why our building process is designed to give you a clear picture of scope and budget before you commit.
We set out the scope, list allowances clearly and explain what could affect the final cost. Whether you are planning a kitchen renovation, a bathroom renovation or a full home renovation, you will know what you are paying for.